Sl. No.
|
Name of ongoing Projects
|
NIT No.
|
Source of Fund (State Plan/BRGF/PSDF/IRF/Special Assistance etc)
|
Remarks
|
1.
|
Supply, erection, testing and commissioning of Reliable
communication and Data Acquisition for implementation of Integrated
Communication system upto 132 KVin Bihar with AMC for 6 years
|
79/PR/BSPTCL/2018
|
State Plan (80:20)
|
|
2.
|
Construction of 03 Nos. of 132/33 KV Transformer Bays in
Biharsharif&Dehri-on-sone Transmission Circle on turnkey basis
|
122/PR/BSPTCL/2018
|
State Plan (80:20)
|
|
3.
|
Construction of 04 Nos of 132KV Line Bays with SAS and
construction of Switchyard Panel Room at 400/220/132KV GSS Saharsa (New) on
turnkey basis
|
01/PR/BSPTCL/2021
|
State Plan (80:20)
|
|
4.
|
Construction of following on turnkey basis under IRF (i)
Construction of 01 Nos. of 132/33 KV Transformer bays each at GSS Nirmali& GSS
Rosera (ii) Construction of 01 No. 220/132 KV transformer bay at GSS Pusauli&
(iii) Construction of new transformer foundation for 50 MVA Power Transformer at
03 locations for transformers
|
46/PR/BSPTCL/2021
|
IRF
|
|
5.
|
Supply, Erection, Testing & Commissioning of DLMS compliant
0.2s class ABT type energy meter with implementation of 100% metering, data
acquisition and online ABT monitoring for the transmission & sub transmission
substations up to 33 KV level, monthly energy accounting and service maintenance
on Turnkey basis
|
09/PR/BSPTCL/2022
|
Special Assistance
|
|
6.
|
Completion of leftover works for Capacity augmentation of GSS
Hajipur, Gopalganj & Darbhanga by replacement of power transformers
|
51/PR/BSPTCL/2022
|
Special Assistance
|
|
7.
|
Augmentation of existing 132/33KV GSS Ekma (1x20MVA +
1x50MVA) by 3x50 MVA capacity
|
36/PR/BSPTCL/2018
|
State Plan (80:20)
|
|
8.
|
Construction of 220/132/33 KV (2x160 MVA+ 3x50 MVA) GSS, at
Garaul (District-Vaishali) complete with SAS including residential quarters
|
39/PR/BSPTCL/2018
|
State Plan (80:20)
|
|
9.
|
Construction of 220 KV D/c transmission line from 220/132/33
KV GSS Chapra(New) ,Amnour to 400/220 KV GSS Muzaffarpur (PG) with Zebra
conductor (line length –Approx. 65 KM)& 132 KV D/c
transmission line from 220/132/33 KV GSS Chapra(New), Amnour to 132/33 KV
GSS Vaishali with Panther conductor (line length- Approx 40 KM)
|
51/PR/BSPTCL/2018
|
State Plan (80:20)
|
|
10.
|
Construction of 02 Nos. 132 KV line bays each at GSS
Muzaffarpur & GSS Vaishali
|
65/PR/BSPTCL/2018
|
State Plan (80:20)
|
|
11.
|
Construction of 02 nos. of 220KV line bays at GSS Motipur& 02
Nos. of 132KV line bay at GSS Runnisaidpur
|
76/PR/BSPTCL/2018
|
State Plan (80:20)
|
|
12.
|
Construction of LILO of one Ckt of 132 KV D/C Kishanganj
(Old)-Forbesganj Transmission line at Palasi GSS with ACSR Panther Conductor
|
69/PR/BSPTCL/2018
|
State Plan (80:20)
|
|
13.
|
Construction of (2x500MVA+2x160 MVA) 400/220/132 KV
GIS New Substation Bakhtiyarpur
|
15/PR/BSPTCL/2019
|
State Plan (80:20)
|
|
14.
|
Construction of (2x200 MVA+ 3x50 MVA) 220/132/33 KV
GSS, Raxaul (District-East Champaran)
|
40/PR/BSPTCL/2018
|
State Plan (80:20)
|
|
15.
|
Construction of Following GIS bays on turnkeybasis.-
1) 02 nos of 220KV GIS bays at GSS Dumraon (BGCL).
2) 01 no of 220KV GIS bay at Darbhanga (DMTCL).
|
44/PR/BSPTCL/2021
|
State Plan (80:20)
|
|
16.
|
Construction of 220 KV double circuit transmission line from
GSS Begusarai to IOCL BarauniRefinery (15 RKM) partly on
monopole tower and shifting of 4 nos. of 220 KV Towers of existing transmission
line required for M/s IOCL on M/C monopole Towers
|
40/PR/BSPTCL/2020
|
Deposit head
|
|
17.
|
Construction of 2 nos. of 220 KV line Bay, demolish of old
quarters & construction of new quarters along with extension of control room and
associated civil works at 220 KV GSS Begusarai under deposit scheme of IOCL
|
24/PR/BSPTCL/2020.
|
Deposit head
|
|
18.
|
Construction of 132KV D/C Raxaul (New)
toRaxaul (old) Transmission line (Line length-20 RKM), 2nd Ckt Stringing of 132
KV Raxaul(Old) -Parwanipur line (07 RKM) & construction of 2 nos. 132 KV Line
Bays at 220/132/33 KV GSS Raxaul
|
05/PR/BSPTCL/2021
|
MEA
|
|
19.
|
Re-conductoring of 12 Nos. 132 KV Transmission Lines with
HTLS equivalent to ACSR Panther conductor
|
14/PR/BSPTCL/2022
|
Special Assistance to States for Capital Investment for
2022-23.
|
|
20.
|
Construction of 02 x 50 MVA 132/33 KV
GSS Palasi with residential quarters. (Dist. – Araria )
under State Plan
|
37/PR/BSPTCL/2018
|
State Plan (80:20)
|
|
21.
|
Construction of 02 nos. 132 KV line bays at GSS Phulparas and
02 nos.132KV line bays at GSS Laukahi on turnkey basis under State Plan
against NIT No:-63/PR/BSPTCL/2018
|
63/PR/BSPTCL/2018
|
State Plan (80:20)
|
|
22.
|
Construction of 132 KV D/C Tr. line by (Line Length-31 RKM) making
LILO arrangement of 132 KV DCSS Benipatti- Pupri Tr. line at Sitamarhi (New)
GSS
& Construction of LILO of Both circuit of Bettiah- Raxaul ,132
KV DC Tr. line at Raxaul (New) GSS (Length-10 RKM)
|
71/PR/BSPTCL/2018
|
State Plan (80:20)
|
|
23.
|
Construction of 132 KV D/C transmission line with
05 Nos. of Pile foundations for river crossing (Koshi) (Route
length-03RKM) required for 33 KV feeder from 132/33 KV
SimriBakhtiyarpur GSS to U/C ALANI PSS (Block-Salkhua) at Saharsa District under
deposit head.
|
04/PR/BSPTCL/2020
|
Deposit head of NBPDCL
|
|
24.
|
(i) Construction of (2x160MVA+3x50 MVA), 220/132/33KVGSS,
Tajpur (Dist.- Samastipur) with SAS including Residential
Quarters.
(ii) Construction of (2x160MVA+3x50 MVA),
220/132/33KV GSS, Thakurganj (Dist.-Kishanganj) with SAS
including Residential
Quarters
(iii) Construction of 220 KV D/C
Transmission Line from PGCIL Banka to
BGCL Goradih with ACSR Zebra
Conductor (Line Length - 39 RKM).
|
49/PR/BSPTCL/2022
|
State Plan (80:20)
|
|
25.
|
Supply, Erection, Testing and Commissioning of 20 Nos. of
50MVA,132/33 KV, Power Transformer and its associated Works by Manufacturers in different GSSs of
BSPTCL under IRF head on turnkey basis
|
40/PR/BSPTCL/2022
|
Special Assistance to States for Capital Investment for
2023-24.
|
|
26.
|
(1)Construction of 132KV D/C
Murliganj-Udakishanganj T/L with Panther Conductor (LL-50 RKM), (2) Construction
of LILO of one circuit of 132KV D/C Ramnagar-Dhanaha T/L with ACSR Panther
Conductor (LL-40 RKM) at GSS Bagaha and (3) Construction of
LILO of both circuits of 132KV GIS Goradih -GSS Sabour T/L (LL-25x2=50 RKM) at
GSS Barari on turnkey basis against NIT No.15/PR/BSPTCL/2021 under state plan.
|
15/PR/BSPTCL/2021
|
State Plan & BRGF
|
|
27.
|
1. Construction of 05 nos. of
132 KV Transmission tower (including 03 nos. of pile foundation)
,stringing with ACSR panther conductor for crossing of 33 KV line from GSS
Ramnagar to PSS Chautarava over Massan River near
Dainmarwa Village and 2. Construction of
02 nos. of132 KV Transmission tower , stringing with ACSR
panther conductor for crossing of 33 KV line from GSS Ramnagar to PSS Bagaha
over Massan River near Juda Villageon turnkey basis under
Deposit Head against NIT-33/PR/BSPTCL/2021.
|
33/PR/BSPTCL/2021
|
Deposit Head
|
|
28.
|
Restoration of 132 KV Kishanganj(New) - Barsoi
DCSS Transmission Line against NIT No - 38/PR/BSPTCL/2020
under IRF head.
|
38/PR/BSPTCL/2020
|
IRF head
|
|
29.
|
132 KV Darbhanga-Phulparas transmission Line with HTLS
Conductor equivalent to panther.
|
111/PR/BSPTCL/2018
|
State Plan (80:20)
|
|
30.
|
Construction of 2x50MVA, 132/33KV GSS Bhorey (Dist.
Gopalganj) with Construction of associated 02nos. 132KV Line bays at GSS Hathua&
Construction of its associated 132KV D/C Bhorey-Hathua Tr. Line with ACSR
Panther Conductor (Line lengh-60RKM)
|
10/PR/BSPTCL/2023
|
State Plan
|
|
31.
|
Construction of 4 Nos of 220 KV GIS bays and 4 nos of 132 KV
GIS bays at 220/132/33 KV GSS Amnour
|
16/PR/BSPTCL/2019
|
State Plan (80:20)
|
|
32.
|
Construction of 2 Nos of 220 KV GIS Bays at 220/132/33 KV GSS
Gopalganj
|
02/PR/BSPTCL/2019
|
State Plan (80:20)
|
|
33.
|
Construction of 132 KV D/C Thakurganj- Araria Transmission
Line with ACSR Panther Conductor and Construction of 220 KV D/C
Kishanganj (New)- Thakurganj Transmission Line with ACSR Zebra Conductor
|
52/PR/BSPTCL/2018
|
State Plan (80:20)
|
|
34.
|
Construction of 132/33kV GSS Jagdishpur (Bhagalpur
New)&Construction of 132/33kV GSS Korha (Dist- Katihar)
|
10/PR/BSPTCL/2016
|
State Plan
|
|
35.
|
Construction of 220 KV D/C by making LILO arrangement of both
circuits of 220 KV D/C Purnea (PG) - Begusarai Transmission line (14RKM)
to 220/132/33 KV Korha GSS
|
70/PR/BSPTCL/2018
|
State Plan (80:20)
|
|
36.
|
Construction of 132/33 KV 2X50 MVA GSS Barari
(Dist.-Bhagalpur), 132/33 KV 2X50 MVA GSS Bagha (Dist.-West Champaran) & 132/33
KV 2X50 MVA GSS Murliganj (Dist.-Madhepura) with 02 Nos. of line bay at GSS
Udakishanganj
|
10/PR/BSPTCL/2021
|
State Plan & BRGF
|
|
37.
|
Construction of single phase 132 KV Transmission line through
underground XLPE cable from GSS Jamalpur to TSS Jamalpur as a spare cable
|
54/PR/BSPTCL/2022
|
Deposit Head of Railway
|
|
38.
|
Construction of 2X 50 MVA, 132/33 KV Grid Sub-station,
Daudnagar (Block:-Daudnagar, Dist-Aurangabad) & 3X 50 MVA, 132/33 KV Grid
Sub-station, Nabinagar (Block:-Nabinagar, Dist-Aurangabad)
|
13/PR/BSPTCL/2021
|
BRGF.
|
|
39.
|
Construction of 132 KV D/C Bakhtiyarpur (New) to Harnaut (BSPTCL) Trans. line & Construction of LILO of 132 KV
S/C Baripahari- Harnaut Trans. line at GSS Barh (Bakhtiyarpur)
|
78/PR/BSPTCL/2018
|
State plan (80:20)
|
|
40.
|
Construction of DCDS 220 KV T/L from Buxar Thermal Power
Plant to GSS Dumraon (New), BGCL with Twin moose conductor.(RL-72 KM)
|
24/PR/BSPTCL/2021
|
Special Assistance
|
|
41.
|
Construction of new 3x80MVA, 132/33KV GIS GSS Mithapur at
Agriculture Research Institute, Mithapur and associated works including
dismantling of existing Mithapur grid Sub station with all associated works.
Construction of 132KV transmission line from new GIS GSS
Mithapur to GSS Karbigahiya through 1200sqmm XLPE underground cable with
associated work including dismantling of existing cable system.(RL- 2.7KM).
|
38/PR/BSPTCL/2021
|
State Plan
|
|
42.
|
Construction of 2X 200 MVA + 2X80 MVA ), 220/132/33 KV GIS at
Digha (New)
|
18/PR/BSPTCL/2019
|
State Plan
|
|
43.
|
Construction of following associated 220KV & 132KV D/C
Transmission Lines of 220/132/33KV GSS Asthawan (Dist. Nalanda) on Turnkey
Basis:-
Line1: Construction of 220 KV D/C Transmission line
from Sheikhopursarai(BGCL) to GSS Asthawan with ACSR Zebra Conductor (Line
Length- 20 RKM)
Line2: Construction of 220 KV D/C Transmission
line from GSS Biharsharif to GSS Asthawan
with ACSR Zebra Conductor (Line Length - 20 RKM)
Line3: Construction of 132 KV D/C Transmission
line from GSS Asthawan to GSS Barh with ACSR Panther Conductor (Line Length - 40
RKM)
Line4: Construction of 132 KV D/C Transmission
line from GSS Asthawan to GSS Rajgir with ACSR Panther Conductor (Line Length -
40 RKM)
Line5:Construction of 132 KV D/C Transmission
line from GSS Asthawan to GSS Nalanda with ACSRPanther
Conductor (Line Length - 30 RKM) Under state plan on Turnkey Basis.
|
58/PR/BSPTCL/2018
|
State Plan
|
Line 1, Line 2, Line 3 & Line 4 completed
Line 5 under progress
|
44.
|
Construction of 04 nos of 220KV GIS bays at GSS
Sheikhpura(BGCL) and 02 nos of220KV GIS bays at GSS Hathidah (Total 06 nos of
220KV bays)
|
08/PR/BSPTCL/2019
|
State Plan
|
|
45.
|
Construction of 02 nos. 220 KV AIS Line Bays at GSS Fatuha
and 02 nos. 132 KV AIS Line Bays at GSS Harnaut.
|
03/PR/BSPTCL/2021
|
State Plan
|
|
46.
|
Construction of 2X 80, 132/33 KV GIS at Board Colony Patna
|
17/PR/BSPTCL/2019
|
State Plan
|
|
47.
|
Construction of 132KV transmission line from 132/33 KV GIS at Board Colony Patna to 220/132/33KV GIS Digha (New) and
from 220/132/33KV GIS Digha (New) to 132/33KV GSS Digha (Old) through Under
ground cable
|
19/PR/BSPTCL/2019
|
State Plan
|
|
48.
|
Successful completion of Balance work of construction of
220KV D/C transmission line Dehri to Pusauli against NIT No. 07/PR/BSPTCL/2020
|
07/PR/BSPTCL/2020
|
IRF
|
|
49.
|
Implementation of SAS for control & monitoring of existing 12
Nos. of 220/132/33 KV substations (Hajipur, Khagaul, Fatuha, Gaurichak,
Begusarai, Bodhgaya, Dehri-on-Sone, Pusauli, Darbhanga, Gopalganj, Madhepura &
Bihta (New))
|
08/PR/BSPTCL/2023
|
PSDF & IRF
|
|
50.
|
Construction of LILO of 132 KV Sonenagar-Rihand (Ckt.-I)
Transmission line at GSS Nabinagar and LILO of 132KV Sonenagar- Chandauti at GSS Daudnagar
|
14/PR/BSPTCL/2021
|
BRGF
|
|
51.
|
R&M of 02 Nos. 220/132 KV GSS Khagaul and Bodhgaya
|
24/PR/BSPTCL/2022
|
State Plan
|
|
52.
|
R&M of 132/33 KV GSS Hajipur, Sheikhpura, Jehanabad and
Banjari
|
25/PR/BSPTCL/2022
|
State Plan
|
|
53.
|
Construction of 04 Nos. 220 KV Line Bays, its erection,
testing & commissioning at GSS Bodhgaya with associated works
|
19/PR/BSPTCL/2021
|
State Plan
|
|
54.
|
Construction of 02 Nos. of 220 KV AIS line bays at
Dehri-On-Sone with associated work mentioned in the scope of work
|
25/PR/BSPTCL/2021
|
State Plan
|
|
55.
|
Construction of 132/33 KV 2X50 MVA GSS Barachatti
(Dist.-Gaya) along with construction of 02 nos. of 132 KV line bays at GSS
Chandauti (new) & 132/33 KV 2X50 MVA GSS Bhore (Dist.-Gaya)
|
11/PR/BSPTCL/2021
|
BRGF
|
|
56.
|
Construction of 132 KV D/C Chandauti (New) to GSS Barachatti
(Dist.-Gaya) Transmission Line and construction of LILO of 132KV
Barhi-Rajgir(L-29) and Barhi- Nalanda(L-28) Transmission lines each at GSS Bhore
(Dist.-Gaya)
|
12/PR/BSPTCL/2021
|
BRGF
|
|
57.
|
Construction of following transmission lines on turnkey
basis:-
1. Construction of DCDS 400KV from Buxar Thermal Power Plant to
Naubatpur (BGCL) with twin Moose conductor.
2.
Construction of DCDS 220KV from Buxar Thermal Power Plant to
GSS Karamnasa with twin Moose conductor.
3.
Construction of DCDS 220KV from Buxar Thermal Power Plant to
GSS Dehri- on -Sone with single Zebra conductor.
|
23PR/BSPTCL/2021
|
Special Assistance + State Plan
|
|
58.
|
construction of following lines :-
(i) LILO of Barh - Patna 400 KV D/C (Quad) Transmission line at
Bakhitiyarpur (new).
(ii) Bakhitiyarpur (new) to Sheikhpura (new) 220 KV D/C
Transmission line.
(iii) Bakhitiyarpur (new) to Hathidah (new) 220 KV D/C
Transmission line .
(iv) Bakhitiyarpur (new) to Fatuha (BSPTCL) 220 KV D/C
Transmission line.
|
77/PR/BSPTCL/2018
|
State Plan [80:20]
|
Line-1, 2 & 3 completed
|